New Launch Buyer Guide

New Launch Snagging and Handover Checklist Singapore 2026

What to inspect at TOP key collection — structural, mechanical, finishes, and documentation — how to lodge defects with the developer, and how the 12-month Defects Liability Period works.

Disclaimer (Block 1): This article is for educational purposes only and is intended to assist CEA-registered property agents in understanding regulatory frameworks. It does not constitute financial, tax, or legal advice. LEVR's calculations are indicative only. Always verify rates and eligibility with your bank, HDB, CPF Board, or a licensed financial advisor before advising clients.

The TOP Key Collection Appointment

When a new launch development receives its Temporary Occupation Permit (TOP), the developer notifies all purchasers by letter to collect their keys. The key collection appointment is typically held at a showroom or the development site within 14 days of the TOP notice. Buyers are required to bring their NRIC, a copy of the Sales and Purchase Agreement, and their solicitor's letter confirming that completion accounts have been settled.

The key collection appointment is the point at which the 12-month Defects Liability Period (DLP) begins. From the date of key collection, buyers have the DLP period to identify and lodge defects with the developer for rectification at no cost. After the DLP expires, defect rectification becomes the owner's responsibility (or the MCST's, for common area defects).

Snagging Inspection Checklist

A systematic snagging inspection covers four main areas: structure and finishes, mechanical and electrical systems, wet areas and waterproofing, and documentation. Buyers should bring a flashlight, a marble or small ball (for floor levelling), and a notepad or phone for photographing defects.

Structure and Finishes

ItemWhat to Check
WallsCracks (hairline vs structural), hollow areas (tap with knuckle — hollow sound indicates de-bonding), uneven plaster, paint blemishes, staining
FloorsHollow tiles (tap each tile), cracks in tiles, uneven grout lines, lippage (height difference at tile edges), use a marble to check for levelness
CeilingsCracks, staining (indicates past water ingress), uneven plaster, paint finish quality
Doors and framesDoors open and close smoothly, latches and locks function, door frames aligned, no gaps between frame and wall, paint coverage on edges and hinges
WindowsWindows open, close, and lock fully, no gaps or draughts around frame seals, glass undamaged, mosquito mesh intact
Joinery and cabinetryCabinet doors aligned and close flush, hinges and drawer runners smooth, handles installed correctly, laminate or veneer finish undamaged
Balcony and plantersFloor finishes, railings secure and at correct height, no cracks in planter walls, waterproof membrane not damaged

Mechanical and Electrical Systems

SystemWhat to Check
Electrical sockets and switchesTest every socket with a plug-in tester or phone charger, all switches operate correctly, circuit breaker DB correctly labelled
LightingAll provided light fittings illuminate, downlights aligned, no flickering
Air-conditioningAll fan coil units power on and cool, remote controls present, condensate drains functioning, no unusual noise
Water supplyRun every tap and showerhead, check hot/cold water supply at each point, adequate water pressure
DrainageWater drains away from every basin, sink, bathtub, and shower without pooling; no gurgling that indicates poor trap venting
Smart home and intercomsSmart home panel powers on, intercom to lobby functional, access card readers at main door work

Wet Areas and Waterproofing

Bathrooms, kitchen, and balcony/planter areas require particular attention — waterproofing failures are among the most costly defects to rectify after DLP expiry because they often require full tile hacking and membrane replacement:

  • Check that floor drains are set lower than the surrounding floor so water flows toward the drain, not toward the wall or door
  • Look for waterproofing membrane curling at tile edges or gaps around pipe penetrations
  • Check toilet pans and cisterns for correct seating and flush function; no rocking
  • Kitchen sinks: check under-sink cabinet for any existing moisture staining from plumbing connections
  • Balcony: pour a bucket of water and observe whether it drains correctly toward the floor trap; no ponding

How to Lodge Defects with the Developer

Developers typically provide a defect reporting portal, app, or physical defect form at key collection. The correct process is:

  • Document everything in writing: Photograph each defect with a timestamp and reference the location clearly (e.g., "Master bedroom east wall, hairline crack from top-right corner of window frame")
  • Submit through the developer's official channel: Use the developer's designated defect reporting system. Verbal reports at key collection are not sufficient — always get written acknowledgment
  • Track responses: The developer is obligated to rectify defects reported within the DLP. Maintain a log of submission dates, developer acknowledgment, and rectification completion
  • Re-inspect after rectification: When the developer indicates a defect has been rectified, inspect before signing off. Do not sign any completion or acceptance form for a defect rectification until the work has been verified

The 12-Month Defects Liability Period

The Defects Liability Period (DLP) is a contractual obligation in the Sale and Purchase Agreement. Under the standard developer SPA prescribed by the Housing Developers Rules, the DLP is 12 months from the date of TOP (not from key collection, though these are usually close together). During this period:

  • The developer is obligated to rectify all defects in the unit that are reported in writing within the DLP period
  • The developer retains 5% of the purchase price until the Certificate of Statutory Completion (CSC) is issued — this retention is the developer's financial incentive to complete outstanding defect work
  • Defects that are reported but not yet rectified before the DLP expires remain the developer's obligation if they were properly documented within the DLP
  • After the DLP expires, defect rectification in the individual unit becomes the owner's responsibility; the MCST assumes responsibility for common area defects until CSC

Documentation to Collect at Handover

At the key collection appointment, buyers should ensure they receive or request the following documentation:

  • All sets of keys (main door, gate, letterbox, car park, facilities) and access cards or fobs
  • Manuals and warranty documents for all installed appliances (oven, hob, washer/dryer, air-conditioning units)
  • Developer's defect reporting form or portal login credentials
  • As-built floor plan of the unit (useful for renovation planning)
  • Copy of the TOP certificate (the developer should provide this on request)
  • Contact details for the developer's after-service team

Frequently Asked Questions

Q: Can I start renovation immediately after key collection?

A: Technically yes — there is no mandatory waiting period after key collection before renovation. However, it is strongly advisable to conduct a thorough snagging inspection before any renovation works begin. Renovation works (especially tiling, painting, or plastering) can obscure original defects and complicate claims under the DLP. Consider completing the snag list and getting developer acknowledgment before committing to renovation contractors.

Q: What happens if the developer refuses to rectify a defect during the DLP?

A: If the developer disputes a defect or fails to rectify within a reasonable timeframe, the buyer may refer the dispute to the Strata Titles Boards or pursue civil action. For new launch condominiums, the developer's DLP obligation is a contractual one enforceable in court. Buyers should retain all written correspondence, photographs with timestamps, and submission confirmations through the developer's defect portal.

Q: Does the DLP cover defects caused by my own renovation?

A: No. The DLP covers defects in the developer's original workmanship and materials. Defects caused by or exposed during the buyer's own renovation works are generally not covered under the DLP. Agents should advise clients to document the original condition of all surfaces before renovation contractors begin any works.

Q: Is the DLP 12 months from TOP or from key collection?

A: Under the standard Housing Developers Rules SPA, the DLP is 12 months from the date of TOP, not from the individual unit's key collection date. In practice, key collection typically occurs within a few weeks of TOP, so the difference is small — but buyers who delay key collection should be aware that the DLP clock started running at TOP, not when they chose to collect their keys.

Q: What if defects appear after the DLP has expired?

A: After the DLP expires, defect rectification in the individual unit is the owner's responsibility and cost. Common area defects remain the MCST's responsibility until CSC is issued. For latent structural defects (defects that were present but not discoverable at the time of inspection), there may be legal recourse under the Limitation Act for up to 6 years from when the defect was or should reasonably have been discovered — but this is a matter for the owner's solicitor to advise on.

Disclaimer (Block 3): LEVR's calculator outputs are estimates based on inputs provided and current regulatory parameters as known at time of publication. They are not a guarantee of borrowing capacity, stamp duty liability, or CPF eligibility. Regulatory thresholds and rates may change. Always verify with IRAS, your bank, or a licensed financial advisor before making financial decisions.

For CEA Agents

Get the 2026 ABSD Rate Guide — free

A quick-reference PDF with every ABSD rate by buyer profile. Updated for 2026 and sourced to IRAS.

Need expert guidance?

Find a verified property agent with a proven track record in your town.

Find an Agent

Model any new launch purchase with LEVR

LEVR calculators cover progressive payment, ABSD, stamp duty, and affordability — no sign-up required.

Essentials tier available. No credit card required.

Or find a property agent near you →